|
Saving Bahia's
Endangered Clapper Rails
September 2007 Update
The US Fish and Wildlife Service finally issued
the Biological Opinion on the Bahia Marsh Restoration project
in August. Its recommendations are exten-sive. We will not only
have to abide by the “Clapper Rail window,” which
al-lows construction in tidal marsh only during the non-breeding
season (Sep-tember 1 through January 31), but the report also
includes a number of other requirements, including having a biologist
survey for Clapper Rails during construction adjacent to the marsh
during the non-breeding sea-son, publishing a fact sheet for construction
workers informing them of Rail impacts, prohibiting dogs, cats,
and litter at the construction site.
Most agencies are trying to move along our application for marsh
restoration project so we can begin construction. We expect to
have most permits by the beginning of October. However, the Homeowners
Association has had our latest draft language for an access easement
in their possession for nearly four months, and have not yet given
us their comments.
On another front, the Marin County Open Space District has begun
work on a new trail to direct people uphill, away from the edge
of the marsh. We com-mented on the environmental documents and
reviewed the alignment of the trail, which seemed to avoid trees.
We have urged the county to obliterate the existing trail when
the new one is completed. This would avoid multiple im-pacts of
the use of two trails.
February 2007 Update
Unfortunately, during the Novato Planning Commission
hearing for MAS’s restoration project, Bahia homeowners
made numerous statements that were based on misinformation. The
stage may have been set by an article in the HOA newsletter which
contained a number of erroneous statements about our project.
The most sweeping error was that Marin Audubon intended to “exclude”
access to the peninsulas on MAS property. The HOA consultants’
testimony also contained errors, such as MAS planned to place
dredged material over the lands where the HOA would have had to
make the cut through our western peninsula. A difficult situation
was made worse when the Planning Commission allowed personal attacks
throughout the hearing and did not stop rambling testimony on
matters unrelated to the property in their jurisdiction. This
distracted from the homeowners’ relevant concerns, such
as the movement of some of the excavated material through the
streets.
MAS’s property -- 55 acres containing three
peninsulas surrounding the HOA lagoon – were formed more
than 30 years ago for houses. At no time has there been anything
stated or written to indicate that it is, or has been, our intent
to exclude access.
Our project was part of the overall project reviewed
by the DFG-certified EIR that was available for review on the
San Francisco Bay Joint Venture Web site. In fact, many comment
letters were submitted to DFG, and the EIR consultants responded
to each comment letter. Many of these letters were from Bahia
residents.
Following our restoration project, people will be
able to access our property as they do now, with the exception
of the 20 acres that will be restored to marsh. To restore the
20 acres of marsh, fill material placed on tidal marsh many years
ago will be excavated and moved to other areas to be vegetated
with native transitional and upland plants. Currently, our property
is largely vegetated with non- native species.
There will be no change to a 75-foot-wide strip
along the lagoon underneath the PG&E towers where people now
fish and walk. Some will will be trucked to Fish and Game lands
to elevate subsided lands and speed the restoration of the tidal
marsh.
We plan to meet with the homeowners to clarify
what our project is and, hopefully, gain the support of some residents.
Those who want the lock/dredge project may always be hostile.
On another front, Marin Audubon is cooperating
with the city of Novato and DFG to address the strong sulfide
odor coming from the far western section of West Bahia. The odor
is due to decaying vegetation trapped in low layers of the ponded
water. DFG is using a biological agent and will cut notches in
the perimeter levee to allow increased tidal flows. As part of
our project, tide gates will be installed to better control the
water levels and increase circulation. It is essential our restoration
project be accomplished this summer to avoid the worst time of
year for plant decomposition, which is late summer.
Finally, a huge thank you to The Forrest and Frances
Lattner Foundation for their grant of $24,000 for replanting the
high tide refuge/transition zone habitat on MAS property at Bahia.
This grant funds planting of native plant species along the marsh
edge to provide cover, nesting and foraging habitat -- important
components of tidal marsh and uplands habitat.
HOW YOU CAN HELP: Write the Novato Community Development Agency,
75 Rowland Way, #200, Novato, CA 94942 in support of our wetland
restoration project or attend
the Novato Planning Commission meeting on Monday, December 18
at 7:30 P.M at the Novato Unified School District Offices
(pdf agenda). If you would like more information, please call
Barbara Salzman, 924-6057 or email bsalzman@att.net.
January 2007 Bahia Update
Great news! On December 28, Judge Michael Dufficy
vacated the court order requiring the Bahia Homeowners Association
(HOA) to provide boat access to the Petaluma River. The project
would have dredged and
permanently converted some 13 acres of tidal marsh that is habitat
for the endangered California Clapper Rail.
After hearing more than three hours of testimony,
Judge Dufficy determined that circumstances had changed dramatically
since the original court order so as to render the project infeasible.
He listed a number of changed circumstances, including: conflicts
with existing Bay Conservation and Development Commission (BCDC)
policies and law; new laws and policies of agencies making permitting
much more difficult if not impossible (the recent State Endangered
Species Act prohibits the Department of Fish and Game (DFG) from
issuing permits to take a fully protected species, which the Clapper
Rail is); different ownership of adjacent lands (owned by MAS)
which limits access; additional requirements by the city of Novato;
uncertainty about whether the project could ever be built, even
if the homeowners could obtain permits, it would be more than
20 years before homeowners would know whether the mitigation requirements
could be fulfilled; and substantially increased project costs
(now estimated to be more than $17 million).
The HOA, represented by attorney, Wanden Traynor,
presented three witnesses: Michael Wilmar former executive director
of the BCDC, Cay Goude, head of the U.S. Fish and Wildlife Service
Office of Endangered Species, and Michael Josselyn, of the HOA
consultants WRA. The opposing side, represented by attorney Michael
Kane, presented declarations from John Zentner, Michael Cheney,
and John Knox that were not made public. They presented no witnesses.
Their other attorney, Gary Raggianti, had dropped the case and
so was not present.
This was a significant milestone for Marin Audubon
Society because we have long opposed the loss of tidal marsh for
a recreational boating and, in particular, the loss of endangered
species habitat by dredging the HOA's tidal lagoon. Our attorney,
Clem Shute, provided important support for the testimony, particularly
with regard to BCDC.
December 2006 - Bahia Lagoon Dredge Update
(from MAS newsletter):
The court hearing for the Bahia Homeowners Association’s
appeal to vacate the order to provide boat access to the Petaluma
River is scheduled for Thursday, December 28, probably in the
morning, but you will need to check closer to the date.
Initially, Judge Dufficy stated he intended to deny
the HOA’s appeal. At the last hearing, however, he modified
his approach and allowed that each side could present three witnesses
at an evidentiary hearing. He acknowledged that he knows little
about the permit process for filling wetlands and endangered species
habitat, and construction for the boat access would place a significant
financial burden on residents. This is an important change in
his approach.
MAS' attorneys, Clem Shute and Tamara Gallanter,
from Shute Mihaly and Weinberger, have submitted two Friend of
the Court briefs and are appearing in court on our behalf in support
of the HOA’s motion to vacate the order. Our legal bills
for this effort are significant. Fortunately, a generous anonymous
donor has helped, but we still need donations.
July 2006 - Bahia Lagoon Dredge Update:
Bahia
HOA goes to court to get dredge/lock order thrown out - Novato
Advance, 7/12/06
June 2006 - Property Update:
The Draft Environmental Impact Report for the
Bahia Marsh Restoration Project has been out for public review,
and the comment period closed on May 20. We expect that comments
will be responded to and look forward to a final approval in late
June or early July so that we can proceed with the restoration
construction.
April 2006 - Property Update:
The DEIR has just been released and can be found
on the Joint
Venture web site for those who want to read it. The review
period will be 30 days after which we hope to move forward quickly
with permitting. If all goes well we will be able to begin construction
this summer or fall.
January 2006 - TIDES TURN AT BAHIA
Opinions are changing at Bahia, as reflected
in responses to a recent survey of the 288 Bahia homeowners. Of
the 240 respondents, 164 or 68%, were opposed to the lock-dredge
project and opposed paying the assessment ($45,000 for off-water
and $90,000 for on-water residents) needed to complete the project;
176 or 73%, indicated this cost would cause financial hardship;
41% indicated they were willing to pay nothing, and 25% were willing
to pay a very minimal amount (between $1 and $100) for monthly
maintenance of the lagoon. Maintenance is an important issue because
there is a real potential for water quality problems with the
design. There are areas where water would stagnate and drop sediments
because they would not flush well. The strong anti-project vote
was likely influence by the recently updated construction cost
estimate which identified the cost in the range of $17 million
instead of the $8 million the receiver had touted for years. This
figure does not even include costs of ongoing maintenance and
management. Bel Marin Keys, that has a similar lagoon system,
had to do expensive dredging after years of neglecting the maintenance
flushing of their lagoon. They now have a manager to maintain
their lagoon and reportedly have the highest taxes in the county.
Interestingly, 142 homeowners (59%) found the
current condition of the lagoon, which is now restored to tidal
marsh, acceptable and 169 or (71%) said they would not even use
the lagoon for boating.
The reasons to revise the court decision are
increasing. They are both biological and economic.
All signs now point to this as the time the
Home Owners Association should go back to the court and request
to be relieved of the order to provide boat access.
January 2005
GRANT NEWS - MAS is thrilled to announce receipt
of a check in the amount of $37,445 from National Audubon Society
to help fund a plan for the property (three peninsulas) that MAS
owns at Bahia. This was a grant from The Orvis Company obtained
for MAS by California Audubon’s San Francisco Bay Program
about a year ago.
The grant funds went to NAS and, for some reason,
NAS took more than six months to release them to us. Our thanks
to Susan Lewis of the California Audubon staff for doggedly pursuing
this on our behalf. We very much appreciate Orvis’ contribution
and that of many of its customers who donated matching funds.
These funds will be combined with funds received from the Forrest
Lattner Foundation and the Marin Community Foundation to complete
the plan.
MAS is also pleased to announce it has been
approved for a grant from the Friends of the San Francisco Estuary
in the amount of $1,300 to fund public outreach for the Bahia
restoration project. Our thanks to the Estuary Project for this
financial assistance.
History of Bahia
The existing Bahia development of 288 houses
(80 on water) was built before the California Environmental Quality
Act, so the very high siltation rate in this area was not disclosed.
Removing the sediment to keep the channel open required unanticipated
frequent dredging. A further complication was that, due to increasing
public concern about the disposal of dredged material in the bay,
regulatory requirements for testing and disposal of dredged material
became more stringent and costly. This further hampered the HOA
dredging. Finally, some of the residents sued to get the HOA to
move ahead on dredging. A Marin County Judge agreed and appointed
a receiver charged with pursuing a project that would provide
boating access to the Petaluma River.
The boat access project has changed over the
years. It originally involved dredging of the HOA tidal lagoon
(surrounded by docks and houses) and channel, but this was later
modified to include a lock, to reduce siltation in the lagoon
and hence the need to dredge. Early on, these projects were combined
with previous owner Condiotti’s Bahia development project. As
the combined plan was unable to get permits, the lock/ dredge
project was separated from the housing proposal and the design
changed: the tidal lagoon would be dredged, a plug placed at the
lagoon mouth to stop tidal action, a channel excavated through
a peninsula (that MAS now owns) to connect the tidal with the
non-tidal lagoon, and a lock constructed for boat access to the
river. This project would still result in the loss of about 12-15
acres of tidal marsh that had been restored within the lagoon
and channel since the last dredging in 1987.
Through about 15 years of project review, the court-appointed
receiver and his attorney repeatedly promised that agency permits
were just around the corner. However, the permits never materialized
because the agencies had problems with the significant impacts
of the project. Costs were mounting and there was no end in sight.
Finally, Bahia citizens’ took matters into their own hands, went
back to the court, got approval to reestablish a Board of Directors,
and elected Board members.
Previous updates:
February 2004
A special thank you to the Forrest Lattner Foundation
for approving a grant of $25,000 to assist in preparing a design
for restoring the 60 acres MAS owns at Bahia. We have applied
to several
other possible funding sources for the additional funds necessary
to complete the design plan. Planning for the 330+ acres now owned
by the Department of Fish and Game is underway. We want to ensure
that planning for the restoration of these sites is coordinated.
On the subject of the lock/dredge project, Judge
Michael Dufficy held a second hearing on January 7, 2004. Dufficy
allowed Marin Audubon to participate as a friend of the court
and an interested adjacent property owner. We were ably represented
by our attorney Clem Shute who spoke to our commitment to protect
the Clapper Rail habitat and difficulties ahead because we will
not permit use of our property for the environmentally damaging
lock/dredge project except the limited use we are required to
provide by agreement made by the previous land owner.
At the first hearing, many homeowners who attended
objected to the receiver, Marshall Levy, and his excessive expenditure
of money. The Homeowners Association now has a deficit of more
than $300,000.
In response to the request of many Bahia residents, Judge Dufficy
directed that an election be held to reinstate a Board of Directors
that will replace Marshall Levy as receiver of the Homeowners
Association and that a special master be appointed to oversee
the election. On the negative side, he allowed Marshall Levy to
spend an additional $20,000 to $25,000 to pay Zentner and Zentner
Associates to conduct surveys for the endangered Clapper Rail.
2003 - The HOA has a new attorney
but has retained the same biological consultant, John Zentner,
who is now the project designer and advisor to the HOA Board on
ways to pursue the lock-dredge project. In an attempt to save
the Clapper Rail lagoon (tidal) and channel marsh habitat, MAS
offered alternatives: (1) MAS purchasing the lagoon and channel,
and (2) allowing access over MAS’s upland peninsula that surrounds
the HOA non-tidal lagoon so that they could construct boat docks
or simply launch their boats into their lagoon. The Bahia HOA
has no legal access to construct or maintain the lock planned
for the end of one of the peninsulas. Our alternatives were of
interest to some residents, but did not win approval.
The HOA is now considering other alternatives:
a phased project that would begin with dredging a 60-foot channel
behind houses in the tidal lagoon, building part of the mitigation
marsh on State Lands property across the river from Bahia and,
the latest version, first constructing the entire mitigation on
the lands across the river. For both these, the lock/lagoon project
would be built after certain criteria are met on the mitigation
marsh. We are waiting for a response to our request to meet with
the HOA Board to discuss these plans.
A major question has been what criteria the
US Fish and Wildlife Service (USFWS), the agency that administers
the federal Endangered Species Act, would require of the project.
That question was answered in part by a September letter from
USFWS describing preliminary criteria for a phased project. The
criteria state that, based on the surveys by Avocet Research Associates
in the Bahia tidal lagoon, seven pairs of Clapper Rails must be
nesting in the mitigation marsh for a period of two years before
the lock project can be constructed.
So after more than 20 years of effort, the Bahia
HOA is not much closer to a resolution to the lock/dredge dilemma.
The primary reason is that the project would be an environmental
tragedy. It would directly destroy viable tidal marsh that is
habitat for a major population of endangered California Clapper
Rail that is declining worldwide, with no guarantee that any similar
habitat would be created. To continue to pursue a lock/dredge
project, the homeowners have to be ready to assume substantial
risks without assurances that they could ever build a project.
Pursuing the project would require a substantial commitment of
time and money well into the future. Getting permits from other
regulatory agencies would take time, probably years, to obtain.
The USFWS’s criteria would not satisfy other agencies, the project
is controversial, and there are still questions about the Zentner
mitigation plan that need to be resolved. The USFWS letter indicated
they may impose additional habitat-based criteria. And the HOA
cannot build or maintain a lock until they obtain legal access
over the peninsula from MAS. A major timing question is how long
it would take to get the seven nesting pairs of Clapper Rails.
A survey conducted by the HOA consultant, John Zentner, identified
seven nesting pairs at the nearby Carl’s Marsh that was restored
about 10 years ago. However, this appears to be an overestimate.
The Avocet Research Associates Survey found one-two nesting pairs
and this is consistent with other surveys of that marsh. There
is no known site where Clapper Rail nesting has occurred sooner
than 10 years after restoration.
An optimistic estimate is that the HOA can expect
to wait close to 20 years before being able to build any part
of their lock/dredge project, if they are able to build it at
all. During that period, the homeowners will be looking at major
costs to construct and maintain the Petaluma River mitigation
site. As far as we know, the HOA has not had a construction cost
update estimate for years, and the existing cost data came from
their previous consultant whose information must be questioned.
Our consultants’ analysis was that the existing figures were a
serious underestimate of costs, let alone the costs of maintaining
and remedying any problems. And, of course, over 20 or so years
the costs of constructing the lock/dredge project would increase
significantly. We have offered to work with the HOA to find a
way that would allow boat access to the Petaluma River, and are
ready to continue, but our goal must be protection of already
functioning endangered species habitat. We are not persuaded to
accept loss of existing habitat by promises of habitat, sometime
in the future, that may never materialize. In our experience,
most mitigation projects are less than successful.
Another alternative would be for the residents
to go back to the judge to ask to be relieved of the responsibility
of pursuing such an environmentally destructive project. The significant
environmental impacts to wetlands, the conflicts with the federal
and state endangered species laws and regulatory agency policy
and regulations, and the burdensome costs would appear adequate
reasons for any judge to take another look at the rationality
of pursuing a project that would provide boat access for a very
limited number of people, and that could have monetary and environmental
costs for the larger population. We are certain the potential
environmental impacts and regulatory conflicts, which have increased
substantially, were never forthrightly presented to the judge.
Novato Advance: "State Rules
May Ban Bahia Dredge" November 2004
Barbara Salzman Editorial on Bahia,
Marin Voice, Marin Independent Journal, November 2004(pdf
file)
Saving
Bahia's Endangered Clapper Rails - November 2004
Now
that Marin Audubon has purchased the 632-acre Bahia that had been
slated for development, we are focusing on developing plans to
restore the wetlands and protect the endangered Clapper Rail population
that inhabits adjacent tidal marshes. In accord with MAS’ long-standing
wetlands protection policy, we have advocated protecting the marshes
at Bahia for the last 20+ years - even before Clapper Rails were
found. Now that Clapper Rails inhabit the channel and tidal lagoon
marshes, our resolve to protect those habitats has strengthened.
We were able, thanks to contributions from generous
donors, to hire biologist Jules Evens of Avocet Research Associates
to survey the 2004 breeding season of Clapper Rails in the North
Bay. This survey pointed out the vital need to protect tidal marshes
that are Clapper Rail habitat, including those owned by the Bahia
Homeowners Association (HOA). The Bahia lagoon and channel support
10-16 pairs of nesting Clapper Rails or 42% of the Petaluma River
population. These numbers were the second highest of all North
Bay sites surveyed. Gallinas Creek has the highest population.
The site is even more important in the light of the dramatic declines
Clapper Rails have suffered in other North Bay drainages. The
Napa River once supported thousands and the best estimate now
is 12 nesting pairs. In 1992, Sonoma Creek supported 13 nesting
pairs; our 2004 survey and a 2001 survey found none.
How We Did It!
This stunning purchase, in 2003, was made possible
by contributions and other support from many, many sources. Our
first donation was from the Marin County Open Space District which
made the first major contribution of $800,000; it recommended
that the Marin Community Foundation use the last $200,000 of the
Open Space Funds, and later we received a donation amounting to
$50,000 from the Supervisors. The Marin Community Foundation approved
a separate grant in the amount of $300,000, making a total donation
of $1.35 million. Our largest donation was from the California
Coastal Conservancy. The final amount contributed by the Conservancy
- $5,820,186 - was not determined until the final amount of donations
from non-state sources could be calculated. The non-state contributions
came from a variety of sources: hundreds of individual donors
and private foundations contributed more than $600,000 to the
Baylands Fund at the Marin Community Foundation. These include
the Forrest C. Lattner Foundation, Rusche Fund, Missimer Fund,
California Native Plant Society, Gabilon Foundation, Marin Conservation
League and the Marin County Wildlife and Fisheries Committee.
This purchase was truly an effort that would
not have succeeded without support, encouragement and funding
of the Marin Baylands Fund at the Marin Community Foundation and
from many agencies as well as many individuals and private foundations.
Marin Audubon thanks each of you for making this triumphant accomplishment
possible!
Audubon
closes deal to save Novato parcelSan Francisco Chronicle
Bahia
featured in Bay Nature MagazineApril/June 2003
Bahia Wetlands & Endangered Species
The following was published in the Marin Independent
Journal in February 2005 as an Op Ed from Barbara Salzman, Marin
Audubon, in response to several letters to the editor objecting
to MAS' position on Bahia. We would like all of our members to
know why this issue is so important to us, and so decided to reprint
it here:
Recent letters to the IJ have attacked me personally
and the Marin Audubon Society, questioning the value of endangered
species in comparison with the recreational benefits to some Bahia
residents. Marin Audubon works hard to protect endangered species
such as the California Clapper Rail and their threatened habitat
at Bahia, because protecting species has broad public benefit.
The Endangered Species Act expressly states that
the preservation of endangered species is important for many reasons,
including the aesthetic, ecological, educational, historical,
recreational and scientific value to our country.
In the Endangered Species Act, Congress recognized
that human activities can threaten the health of the environment,
and thus all of us, and pledged that the United States would conserve
species facing extinction, pursuant to at least seven international
treaties to which each of us is a party by virtue of being a citizen
of this country.
Healthy ecosystems depend on plant and animal
species as their foundations. When a species becomes endangered,
it is a sign that the place - the place where you live - is also
becoming endangered. There is a domino effect - each species that
is lost triggers the loss of other species within the ecosystem.
Neither you nor your children are exempt from this process.
Wetlands - and the Clapper Rail as an indicator
of their health - are prime examples of how you benefit from the
protection of habitat and endangered wildlife. Without healthy
wetlands you would not have fish to eat, ponding areas for floodwaters,
clean water to drink or swim in, or clean air to breathe. The
Marin economy also benefits from the 200 million people who visit
our wetlands and other open spaces every year. The tragic decline
of the Clapper Rail, caused by the destruction of San Francisco
Bay wetlands, is a symptom that you are on the verge of losing
these benefits.
Healthy ecosystems mean we still have the chance
of finding a cure for illnesses for which there is no known cure,
maybe even helping someone you know. More than 50% of the 150
most prescribed medicines were originally derived from a plant
or other natural products. Only about 5% of known plant species
have been tested for medicinal uses.
Nor can we overlook the fact that we all share
the earth with these species. They are part of the complexity
of nature. Observing them brings us challenge and enjoyment and
contributes to the scientific understanding of the earth and our
evolution.
As for Marin Audubon's impact on Bahia's permitting
process, agencies listen to Marin Audubon because we have a proven
track record of providing well-informed, credible and responsible
input. The notion that Marin Audubon is responsible for Bahia's
lack of permits is ludicrous. We offered solutions not roadblocks.
Bahia's lock-lagoon project has not been able to get permits because
it is a bad project environmentally.
To correct other inaccuracies, Marin Audubon
has no 'in-house' biologist. We hire qualified, independent ornithologists.
In our experience, wetland mitigation projects are rarely successful,
unlike wetland restoration projects. There is a difference in
the project purpose and the applicants' motivation. Bahia' s flatlands
were tidal marsh prior to being diked or excavated and Marin Audubon
has never recommended tearing down houses at Bahia. Finally, we
don't have swamps. Swamps have trees, wetlands do not.
If anyone believes their misleading statements
and false accusations will deter Marin Audubon, or me, from our
mission, they are mistaken. The stakes are too high. Once the
last of a species dies, there is no turning back, no second chance.
All photographs copyright tdnuerf, 2003. |